As I indicated in one of the responses, I don’t have the list of individuals that were paid out or the circumstances surrounding the payout. What I’m dealing with is the payout of a company, Rowe’s Construction, at this point. What we’re indicating is that we have the money to finish the bridge, clean up all the deficiencies. If we’re going to pay over and above that, if we’re going to pay for a deal that somebody made with another company that went bankrupt on the job, then we’d have to come back to the House for more money. It’s that simple. We can’t take money out of there and then pay somebody and then come back in here and say we need more money for deficiencies.
Tom Beaulieu on Question 935-17(5): Deh Cho Bridge Referee Claim Review
In the Legislative Assembly on October 6th, 2015. See this statement in context.
Question 935-17(5): Deh Cho Bridge Referee Claim Review
Oral Questions
October 5th, 2015
See context to find out what was said next.