We have just over a month of time to do this work. That's not a lot of time, especially with the warm weather coming closer. As I mentioned, Housing actually is stockpiling gravel in the community, but the contractor is not planning to put this road in place due to the cost of the next couple of years. So I strongly encourage the Minister and the department to ensure that they stockpile enough for the next couple of years here. They will be making the road up to the bridge site, but it's not planned up to the gravel source. Thank you.
Frederick Blake Jr. on Question 809-17(5): Willow River Bridge
In the Legislative Assembly on March 12th, 2015. See this statement in context.
Question 809-17(5): Willow River Bridge
Oral Questions
March 12th, 2015
Page 6191
See context to find out what was said next.