I want to make a comment on the Member's statement earlier today about the weather and the conditions in the Beau-Del there. I said it's been very challenging for all contractors in the region and I appreciate all the work they've done to get the work done that they did this year. We will be finishing up the border to kilometre 74 to Peel River Crossing this year because that work isn't completed. The section of highway from 60.5 to 61 will be lifted and that work is to be carried out over the next summer, and also in the next season we will be resurfacing the crushed gravel from kilometre 30 to kilometre 74.
Wally Schumann on Question 345-18(2): Dempster Highway Widening Project
In the Legislative Assembly on October 18th, 2016. See this statement in context.
Question 345-18(2): Dempster Highway Widening Project
Oral Questions
October 18th, 2016
See context to find out what was said next.