Thank you, Mr. Chair. So the project is not ahead of schedule it's just on time per the schedule that was provided for during the procurement process by the successful proponent, Boreal Health Partnership. When the government first procured -- were investigating and preparing the project, we were anticipating a five-year construction period. Boreal came back with a four-year construction period, and now we're just adjusting our cash flows to match that construction period. Thank you.