Thank you, Mr. Chair. I do have opening remarks. I'm here to present Supplementary Estimates (Infrastructure Expenditures), No. 2, 2016-2017. These estimates provide for an increase of $18.8 million to the capital budget. These Supplementary Estimates include:
● funding of $15.3 million for a change in the timing of expenditures expected for the Stanton Territorial Hospital Renewal Project, the total cost of the project has not changed.
Amongst other items, these supplementary estimates also include:
● funding of $2 million to begin work on the heavy equipment operators facility project at the Aurora College Thebacha Campus;
● funding of $804,000 for replacement of the aircraft rescue and firefighting truck at the Yellowknife Airport; and
● funding of $419,000 to start the expansion of Ecole Allain St-Cyr School in Yellowknife.
That concludes my opening remarks, Mr. Chair. Thank you.