Thank you, Mr. Chair. Mr. Chair, the plan for the extended care beds is that, once the new hospital is completed and the services are moved into the new building and the old hospital is vacated, we will then work with the property manager of that building, who will do the capital asset retrofits on that building to meet our specs and our needs.
Our costs on this would be structures and beds and other medical equipment, which is a capital purchase, but not necessarily the cost of doing the changes on that building. That should start, design is expected to start, in early 2018. Construction is expected in late 2019 after they move out of there, and we're hoping to be in there by eighteen months after we start the retrofit of that building to meet the extended care needs.