Thank you, Mr. Chair. Mr. Chair, we will have staff in the building doing mock runs of processes, mock runs of other things. Some of the structure, furniture, et cetera, will be moved in, but for warranty purposes we would obviously be looking at putting off or moving the substantial amount of the furniture until sort of the last minute in order to make sure that we have insurance coverage and we're not wasting warranty time or insurance time, warranty time on facilities that are sitting in an empty building.
It will progress in, and not all divisions or sections are going to move in at the same time. That would never work. We're going to phase a move-in, so different units at different times. The units that obviously have some crossover, we'll want to coordinate those so that we're moving them in in a coordinated, logical fashion. It will all be planned out, phased out, in light of demands in different units, staffing, equipment, when we want to move those types of things in.