Thank you. The six-month period of operational readiness is, as the Minister mentioned, when we will phase in moving all the programs over, having the staff have the opportunity to run through the processes, having the equipment tested and set up, so that once we get to the targeted first-patient day, which will be, you know, around May or June of 2019, then we can actually then move the patients in; but the staff have to have a chance to run and function in the new facility to make sure everything works as designed, and then we can make any adjustments as needed before we actually move all the patients in.
All the various programs in the building will be moving in, as the Minister said, in phases, and they'll test this department and test that department and make sure that all the systems in the building are running correctly before we actually move any patients in.