You’re quite correct. There certainly has been a lengthy delivery in the delivery of these generators as I mentioned. The prior question, I am hopeful that we will receive them. I believe that the plan is that should there be additional costs, we will seek compensation from Virdi Power. There may be issues in being able to do because of Virdi’s situation, but there should be a set-off of any money that we owe them for any additional costs that we have incurred. Thank you, Mr. Speaker.
Louis Sebert on Question 924-18(2): Replacement Generators Contract And Costs
In the Legislative Assembly on October 3rd, 2017. See this statement in context.
Question 924-18(2): Replacement Generators Contract And Costs
Oral Questions
October 2nd, 2017
See context to find out what was said next.