Thank you, Mr. Speaker. Mr. Speaker, we are expecting that substantial completion of the facility will be either late November or early December, at which point the government will take possession of the building. It does require that the Department of Infrastructure go in there and do some testing on some of the functional components of the building to make sure that it is all running properly. Once that has been verified, then the Department of Health and Social Services would take over the responsibility of the building. We would then go in there and start doing our assessments on some of the medical equipment and medical tools that are in that building before we start moving in. We are hoping to be fully operational in that building late spring, early summer at the very latest.
Glen Abernethy on Question 6-18(3): Sahtu Regional Health Centre
In the Legislative Assembly on October 17th, 2017. See this statement in context.
Question 6-18(3): Sahtu Regional Health Centre
Oral Questions
October 16th, 2017
See context to find out what was said next.