Question 26-18(3): Modular Public Housing Units
Oral Questions

October 18th, 2017

Julie Green

Julie Green Yellowknife Centre

Mahsi, Mr. Speaker. Mr. Speaker, my questions are for the Minister responsible for the NWT Housing Corporation. In the summer of 2016, her department awarded a contract of Concept Energy Services in Hay River to construct 19 modular duplexes to communities throughout the NWT. How many of those duplexes have been completed and how many have been shipped to their destinations? Mahsi.

Question 26-18(3): Modular Public Housing Units
Oral Questions

The Speaker

The Speaker Jackson Lafferty

Minister responsible for the Northwest Territories Housing Corporation.

Question 26-18(3): Modular Public Housing Units
Oral Questions

Caroline Cochrane

Caroline Cochrane Range Lake

Thank you, Mr. Speaker. Today, what we have is eight of the 19 buildings are now partially completed. We have three that are in Ulukhaktok, one in Inuvik destined for Fort McPherson, and four are now under construction in Concept's Hay River facility. Thank you, Mr. Speaker.

Question 26-18(3): Modular Public Housing Units
Oral Questions

Julie Green

Julie Green Yellowknife Centre

Unfortunately, the contract is not publicly available, or at least I can't find it. Can the Minister tell me whether the completion rate, that is an eight out of 19, and the partial completion meet the terms of the contract with Concept Energy Services?

Question 26-18(3): Modular Public Housing Units
Oral Questions

Caroline Cochrane

Caroline Cochrane Range Lake

No, the original contract completion dates were between March and June 2017. There were some delays that have been happening, so at this point they have not met the completion date.

Question 26-18(3): Modular Public Housing Units
Oral Questions

Julie Green

Julie Green Yellowknife Centre

What action is the Minister taking to either revoke the contract with Concept Energy Services or work with Concept Energy Services to have the terms and conditions met?

Question 26-18(3): Modular Public Housing Units
Oral Questions

Caroline Cochrane

Caroline Cochrane Range Lake

At this point, the Northwest Territories Housing Corporation is exploring all of the options that are available to us to ensure that all of the houses actually meet their needs within the communities. Our number one foot priority is to ensure that homes are in communities. That is why some of the units actually were pulled into Ulukhaktok and like I say, partially completed as the Honourable Member pointed out, because we were conscious that they needed to meet the barge. So we are working diligently. Our number one focus is to make sure that we have houses in communities. Thank you, Mr. Speaker.

Question 26-18(3): Modular Public Housing Units
Oral Questions

The Speaker

The Speaker Jackson Lafferty

Masi. Oral questions. Member for Yellowknife Centre.

Question 26-18(3): Modular Public Housing Units
Oral Questions

Julie Green

Julie Green Yellowknife Centre

Thank you, Mr. Speaker. Mr. Speaker, I would be interested to know whether the Minister can make the contract available so that we on this side can see what the terms and conditions are. In addition, I wonder if she could tell us whether these units were paid for in advance or whether they are going to be paid for when they are complete. What is the situation with the money? Thank you.

Question 26-18(3): Modular Public Housing Units
Oral Questions

Caroline Cochrane

Caroline Cochrane Range Lake

I believe those were two questions, but I will answer them. I do apologize. I had said that the contracts would be available on the procurement website and for some reason, I have learned that there is some issue with not getting them on there. If the Member would like, I will be able to provide her with a manual copy of the contract. I will commit to doing that.

As for the money, some money was provided up front to help. It is not a normal practice, but it was provided up front to support the manufacturing strategy and recognizing that this is a new strategy that we are trying. To date, though, there is no upfront money. The money has been recouped for the work done, so there is no money that is with Concept at this point that is owing to the Northwest Territories Housing Corporation. We will not make any further payments until the products are complete or near completion. Thank you, Mr. Speaker.

Question 26-18(3): Modular Public Housing Units
Oral Questions

The Speaker

The Speaker Jackson Lafferty