The goal of the project was to validate the integration of solar with significant storage capacity and test the limits of integrating intermittent renewable energy sources. NTPC has contracted with a third party to complete a performance review of the hybrid plant at Colville Lake, to be completed at the end of March 2018. Once the study is complete, the design basis for a standard energy storage system will be completed for consideration and other NTPC thermal power plants.
Louis Sebert on Question 91-18(3): Colville Lake Solar Power Project
In the Legislative Assembly on February 13th, 2018. See this statement in context.
Question 91-18(3): Colville Lake Solar Power Project
Oral Questions
February 12th, 2018
See context to find out what was said next.