Yes, there is set-off for some of the costs that we have incurred as a result of the late delivery, in fact, non-delivery of the last two generators. It is expected that overall, however, that the $8 million budget that was anticipated for this will be exceeded by about $500,000. I think the only way of collecting the extra money would be to commence litigation against Virdi. There was a set-off on some of the payments to Virdi, but I don't know whether it will be worthwhile to litigate this in California.
Louis Sebert on Question 215-18(3): Costs Related To Delay In Delivery Of Generators
In the Legislative Assembly on March 7th, 2018. See this statement in context.
Question 215-18(3): Costs Related To Delay In Delivery Of Generators