As I mentioned earlier, there was a set-off, so money for the costs that were incurred by the late delivery of the first three generators was recovered. There are going to be ongoing costs. That is acknowledged. Our expectation, however, is that the overall original or the expected budget of $8 million will be exceeded by about $500,000. We are looking into whether we can recover additional funds from Virdi Power, but as I mentioned earlier, that is a complex issue. If there is litigation, we would have to look at the cost and time that that might take, and in fact which jurisdiction it would be held in.
Louis Sebert on Question 222-18(3): Northwest Territories Power Corporation Generator Procurement And Cost Overruns
In the Legislative Assembly on March 8th, 2018. See this statement in context.
Question 222-18(3): Northwest Territories Power Corporation Generator Procurement And Cost Overruns