Thank you, Mr. Speaker. The direct construction cost, I think the Member made it in her statement before, $185 million. The total capital cost of $214 million, that would include the crude interest, predevelopment costs, and also GNWT costs for geotechnical studies, the EA process, project management, and provide funding for the measures resulting from the EA process Thank you, Mr. Speaker.
Robert C. McLeod on Question 625-18(3): Tlicho All-Season Road Costs
In the Legislative Assembly on February 27th, 2019. See this statement in context.
Question 625-18(3): Tlicho All-Season Road Costs
Oral Questions
February 27th, 2019
Page 5091
See context to find out what was said next.