There is no cap for northern contractors bidding on projects. We welcome bids from northern contractors on all projects, but I think what the Member is referring to is the BIP adjustment within the BIP policy, which adds up the contracts to up to $1 million and over $1 million. I will read it all in verbatim, just for the public.
Section 8:
(8) Application of Bid Adjustment
Contracts Less than $25,000
Whenever possible, goods, services and construction valued at less than $25,000 should be purchased directly from BIP Businesses in the Local Community, but no bid adjustment will be applied.
Contracts equal to or more Than $25,000 and Less Than $1,000,000
(i) A 15 percent Bid Adjustment will be applied to the NWT Content. An additional 5 percent Bid Adjustment will be applied to any Local Content.
Contracts Equal to or More Than $1,000,000
(i) For the first $1,000,000, a 15 percent Bid Adjustment will be applied to the NWT Content and an additional 5 percent Bid Adjustment will be applied to any Local Content.
(ii) For that portion of the contract above $1,000,000, up to the maximum allowable bid adjustment:
a. 1.5 percent Bid Adjustment will be applied to the NWT Content;
b. an additional 0.5 percent Bid Adjustment will be applied to the Local Content.
The maximum bid adjustment for all bidders on northern or local content is $500,000. So that the Member is also aware, in 2018-2019, the GNWT had contracts of 1,501 contracts, and only 46 of them were above $1 million. Thank you, Mr. Speaker.