Thank you, Mr. Chair. The status of that is they have done a feasibility report on that. New modular gas-generating plant and LNG storage and vaporization facility on the parcel of land outside the downtown core in Fort Simpson. Design basis engineering work has shown that the total project cost would be $13 million. This is much higher than the Inuvik project due to the fact that Fort Simpson is a greenfield project with no existing gas infrastructure. This is one of the infrastructure projects slated for funding under federal infrastructure funding. Thank you, Mr. Chair.
Robert C. McLeod on Consideration In Committee Of The Whole Of Bills And Other Matters
In the Legislative Assembly on August 22nd, 2019. See this statement in context.
Consideration In Committee Of The Whole Of Bills And Other Matters
Consideration In Committee Of The Whole Of Bills And Other Matters
August 22nd, 2019
Page 6408
See context to find out what was said next.