Thank you, Madam Chair. For Mangilaluk School, the contract was awarded to the Inuvialuit Development Corporation late this past summer. In early September, we received the construction schedule and foundational review for phase 1. For late September to October 2020, there was the mobilization of personnel to site and basic preparatory site works. For the timeframe we are in right now, which is slated to run from October till November 2020, the contractor is working on putting the pilings in place. Thank you, Madam Chair.