Thank you, Mr. Speaker. The Member is correct, it's four that have been completed, and we have 51 right now that I had said that are either -- they're in the process right now either being awarded or completed. The thing that has slowed us down as the Housing Corporation is the delivery of material coming to the territory and also the transfer of the funding from and the agreement finally signed by the federal government. So we actually do have the federal funding that is -- that we do have as a corporation. We will be looking at the unit delivery.
The other information I want to provide to the Member is the completion of the 90-unit delivery should be year 2023-2024. All units should be built, and people should be living in them. Thank you, Mr. Speaker.