Thank you, Madam Chair. Madam Chair, the replacement of this bridge is very critical to the transportation, especially people coming in and out of Yellowknife.
The GNWT has secured about $37.5 million under the Transport Canada's National Trade Corridors Fund. So, you know, right now we need to replace the bridge. I mean, we've got reduced speed limit across the bridge and I just really encourage people to continue to follow that -- the kilometer that we've identified when crossing the bridge.
Some of the work that's planned for 2022-2023 is contractor mobilization, site preparation, road realignment, embankment, construction. Also some granular material production, procurement of steel piping, steel fabrication. So Madam Chair, there is work that's being done as well. Also we have an agreement with the Tlicho, you know, going forward in these projects. Thank you, Madam Chair.