Thank you very much, Mr. Speaker. Mr. Speaker, the Prohibition Creek access road is one of our priorities of this Assembly and therefore it's something that we need to advance.
We did receive some funding from the federal government, ICIP funding that brings us -- you know, the ICIP program goes until 2028. We're still in process of phase 1. The project's broken up into two phases. The first phase includes the seven kilometre portion from Canyon Creek to the Christina Creek. The second phase is to include the remaining six kilometres of Christina Creek to Prohibition Creek. So right now, we're still in the procurement for the construction of the first phase. So we're still in that process. Thank you, Mr. Speaker.