Thank you, Madam Chair. Under contract services, we actually have a decrease of $379,000 but we have interior window caulking that we had planned to do for $40,000; fuel tank membrane replacement of $50,000; roadway and walkway trail maintenance at $25,000; window replacement for Caucus of $30,000. Ms. Wickens may have some additional comments as well. Thank you.
Frederick Blake Jr. on Committee Motion 197-19(2): Tabled Document 561-19(2): Main Estimates 2022-2023 - Executive and Indigenous Affairs - Deferral of Department, Carried
In the Legislative Assembly on March 8th, 2022. See this statement in context.
Committee Motion 197-19(2): Tabled Document 561-19(2): Main Estimates 2022-2023 - Executive and Indigenous Affairs - Deferral of Department, Carried