Thank you very much, Mr. Speaker. Mr. Speaker, I'm going to correct the Member to say that we have six hydro turbines that are ranging in size from 8 megawatts to 500 kilowatts. So I want to talk a little bit further because I think this is important.
Over at the Snare Rapids plant, we have completed a large -- an overhaul on unit number 2 back in 2022, and it's expecting to complete an overhaul on unit 1 in the next five years. Over at the Snare Falls plant, we completed an overhaul in 2017. At the Snare Cascades plant, which is owned by Tlicho and we lease it through -- at the Northwest Territories Power Corporation, an overhaul is expected to be completed in the next five years. And finally at our Snare Forks plant, Northwest Territories Power Corporation completed an overhaul on unit 1 in 2021, and we're expected to complete an overhaul in unit 2 in the next five years. So we are doing work at the Snare plants. Thank you, Mr. Speaker.