That's pretty good. That's a pretty quick turnaround. I will be genuinely surprised if we complete this on time and on budget in 2026, whatever that budget may end up ultimately being.
I guess back to my previous point, I could do this for every single capital project - you know, is there federal money, when is it starting construction, when is it completing construction, what are you doing with the initial assessment, how is it being procured, how much is the total budget -- I've never gotten an answer to that one but, you know, one day hopefully.
I would encourage the GNWT, before it comes and asks for millions of dollars from the legislature, to just state those basic answers. I find it very odd that the way we announce we're building a fire centre is with a one-line item in this. It's a good news story. It's very odd that we don't answer those basic questions before asking for millions of dollars.
I guess, in the form of a question, when can we expect to know how much this fire centre is going to cost us? Thank you.