Thank you, Mr. Chair. I don't have the detailed information either, but what I can say is what's being proposed in this supplementary request is to re-cash flow $500,000 for this project to a future year to better match those project schedules. I know the department was doing some work at the community level to determine the best timing for that project in relation to potentially moving the larger diesel plant. That was a conversation that came to light after the Fort Simpson flood two years ago, and I think the department is still working through that conversation with NTPC. Thank you, sir.
Mr. Terence Courtoreille on Consideration In Committee Of The Whole Of Bills And Other Matters
In the Legislative Assembly on February 26th, 2024. See this statement in context.
Consideration In Committee Of The Whole Of Bills And Other Matters
Consideration In Committee Of The Whole Of Bills And Other Matters
February 26th, 2024
Page 244
Terence Courtoreille
See context to find out what was said next.