Thank you, Mr. Speaker. The warehouse Mr. Gargan is speaking about was postponed because the tender call received only one submission. Due to the lateness of the tender -- the bid was $411,000, which exceeded the budget figure. Attempts to negotiate with the contractor were unsuccessful. At the present time, the Housing Corporation is looking at the availability of facilities in Fort Providence. We are also looking at a method of construction that will bring the cost down. Thank you.
Don Morin on Question O113-12(2): Financing Construction Of New Warehouse, Fort Providence
In the Legislative Assembly on February 21st, 1992. See this statement in context.
Return To Question O113-12(2): Financing Construction Of New Warehouse, Fort Providence
Question O113-12(2): Financing Construction Of New Warehouse, Fort Providence
Item 5: Oral Questions
February 20th, 1992
Page 92
Don Morin Tu Nedhe
See context to find out what was said next.