Mr. Chairman, for the renovations and upgrade of the Stanton Yellowknife Hospital, the project costs include the work to be done, architectural fees, and the design. The construction portion is around $820,000. The equipment relative to this project was approved prior, in the summer, and I believe it costs about $340,000 for capital equipment. So the equipment required is on site and ready to go for the spaces that are being renovated. Thank you
Mr. Norwich on Item 18: Consideration In Committee Of The Whole Of Bills And Other Matters
In the Legislative Assembly on March 26th, 1992. See this statement in context.
Item 18: Consideration In Committee Of The Whole Of Bills And Other Matters
Item 18: Consideration In Committee Of The Whole Of Bills And Other Matters
March 25th, 1992
Page 478
Norwich
See context to find out what was said next.