Thank you, Mr. Chairman. Both projects, in our view, have to go in at the same time. The water supply project is mainly predicated on the growing population and the need to provide the supply infrastructure to continue servicing the growing community and position itself to service the expansion area. The sewage project is mainly driven by environmental and public health concerns. We've carried through with these projects through the planning and design stage and we're just now, coincidentally, in the construction phase of both.
Mr. Christensen on Committee Motion 76-12(4): To Adopt Recommendation 13, Carried
In the Legislative Assembly on December 7th, 1993. See this statement in context.
Committee Motion 76-12(4): To Adopt Recommendation 13, Carried
Item 18: Consideration In Committee Of The Whole Of Bills And Other Matters
December 6th, 1993
Page 498
Christensen
See context to find out what was said next.