Mr. Dent is correct. In 1992, Highway 2 did receive an asphalt pavement overlay. Recent inspections by the department staff reveal that the overlay is deteriorating prematurely. This premature deterioration was caused by improper asphalt overlay mix. The department, with the legal division, is evaluating options for recourse with the contractor and site engineers. We need to do this to prevent further deterioration, Mr. Chairman.