Madam Speaker, to my understanding, this sequence of events in this case were rather unusual. It is not something that usually happens. The action that is necessary has been undertaken to deal with the design shortcomings on the Wartsila and the CAT. What has been done is a remote control system for the separate EMD plant is in its final installation stages. We expect that, with the completion of all these initiatives, the reliability of the Iqaluit electrical system should continue to improve and be set for the support of the new capital of Nunavut. Thank you.
Nellie Cournoyea on Question 248-12(5): Reason For Length Of Power Failure In Iqaluit
In the Legislative Assembly on March 2nd, 1994. See this statement in context.
Further Return To Question 248-12(5): Reason For Length Of Power Failure In Iqaluit
Question 248-12(5): Reason For Length Of Power Failure In Iqaluit
Item 5: Oral Questions
March 1st, 1994
Page 471
Nellie Cournoyea Nunakput