Thank you, Mr. Speaker. I have a written question about the PeopleSoft Project. The government may recognize the question, as I have asked it before.
The PeopleSoft Project is consuming significant GNWT resources but does not seem to be meeting the original objectives for a new human resource system. The Minister is asked to provide the following information:
- Chronology of the history of the PeopleSoft Project from the initial decision to replace GHRS to now.
- A list of GNWT staff who have been involved with the project from its inception including the length of time they have been working on the project.
- A list of all contracts and consultants hired for this project from its inception, including the place of origin and the total cost for each one.
- A detailed list of all costs over $10,000 associated with the project from its inception.
- A comparison of the original project cost estimates and schedule to the actual cost and schedule to date.
Thank you, Mr. Speaker.