Mr. Chairman, the $400,000 and another $400,000 this year and $200,000 next year were identified to relocate the solid waste site. However, the road that gives the community the option to relocate was not constructed so the community has to re-examine its plans for the solid waste site. Thank you.
Vince Steen on Committee Motion 3-14(6): To Cease Work On The Main Street Paving Program Until Baseline Data On Dust Levels And Health Information Can Be Collected, Carried
In the Legislative Assembly on February 21st, 2003. See this statement in context.
Committee Motion 3-14(6): To Cease Work On The Main Street Paving Program Until Baseline Data On Dust Levels And Health Information Can Be Collected, Carried