Thank you, Mr. Speaker. Mr. Speaker, I am encouraged by the fact that the Minister is indicating that they are dealing with the federal Minister on this. I certainly hope that a company like Western Geco will stay the course and be willing to come back next year. There is still no guarantee that they are going to get their permits for next year. Would the Minister indicate if he feels that a full review of the Mackenzie Valley Resource Management Act is warranted due to the delays that we are experiencing now?
Paul Delorey on Question 264-14(6): Delays Caused By Regulatory Process
In the Legislative Assembly on June 6th, 2003. See this statement in context.
Supplementary To Question 264-14(6): Delays Caused By Regulatory Process
Question 264-14(6): Delays Caused By Regulatory Process
Item 6: Oral Questions
June 5th, 2003
Page 850
See context to find out what was said next.