Thank you, Mr. Chairman. It's a real pleasure to see a project, and if I have my information right, that's going to be completed ahead of time and on budget. The question I wanted to ask here is, of course, on the airport passenger terminal building project in Yellowknife. We're not changing the overall cost of the project, but because of advances in completion, we need $2.8 million to spend this current year, and not next year when it was originally booked. My question, Mr. Chair, is, how is this acceleration achieved? As I say, it's good to see, but we're still sort of five months out from the end of
the fiscal year. It seems that a lot of work was done earlier than, perhaps, projected, and I would just like to get a little detail on what happened either in the construction, or the planning, or the scheduling, that caused this variance. Thank you.