Thank you, Mr. Speaker. My apologies. I am trying to get in as many questions as I can here, as question period has expired. One of the more alarming things in that audit was there was a change order for the contract in 2002-03 for the amount of $25,000. There were no reasons given for this increase, or the changes associated with that increase. Can the Minister explain to me, under what circumstances can somebody just change a sole-source contract and increase that contract by, in this instance, $25,000? How can that happen? Thank you, Mr. Speaker.
David Ramsay on Question 282-15(4): Contract Administration And Accountability
In the Legislative Assembly on October 26th, 2005. See this statement in context.
Supplementary To Question 282-15(4): Contract Administration And Accountability
Question 282-15(4): Contract Administration And Accountability
Item 6: Oral Questions
October 25th, 2005
Page 570
See context to find out what was said next.