Thank you, Mr. Chair. Mr. Chair, this project was undertaken quite some time ago initially. It was constructed over a number of years. It was a negotiated contract with oversight from Public Works and Services. They received substantial completion in May of 2004 where it was turned over to the community of Whati. It was in January of 2005 that the flooring became a problem and progressively worsened to the point of safety concerns were raised.
In our discussions with the contractor about the work and the need to do the right work, there was some initial activity done to try and remedy it. That did not fix the problem. In the meantime, as things happened with the Tlicho Government coming into effect and taking over the company that was involved, it has further complicated the matter. But we are in discussions again about where we need to go and try to recover these costs. Thank you.