Thank you, Mr. Chairman. We've been able to reach an agreement with the fire marshal that if we will do approximately $525,000 worth of renovations to the existing hall and promise that we'll be out by May of 2008, that we won't have to spend the $3 million that we had come forward for repairs previously. So we've been able to turn this project around from a short-term renovation into long-term replacement of the building. We expect to be able to have the new building in place to replace that before May of 2008. The total price for the building will be about $8.6 million. We're hopeful that it will be in that range. Thank you, Mr. Chairman.