Cost overruns on a project — on any project in the Northwest Territories — are a real factor that we have to look at, in terms of the potential impact it may have on us as the Government of the Northwest Territories and our future ability. That's why, as part of the agreement signed during the previous government, a guaranteed maximum price was put in place, as were a pre-funded contingency, insurance, bonding, an independent engineer auditing the construction, and a project management board made up of the Government of the Northwest Territories, the Deh Cho Bridge Corporation and the lending agency that's involved in this. So those factors have been put in place.
As for the request to look at what that impact may be — if I understood the question correctly — of us withdrawing from the process, we shall endeavour to get that information.