Thank you, Mr. Chair. I
hope one day we can put a hydro line into Colville Lake. For the Taltson hydro expansion there were a number of routes outlined in 2002 and 2003. Some of the routes were ruled out either for technical reasons or project financial viability. These were being studied.
The Taltson proponents, the Deze Energy Corporation, received the terms of reference for a development assessment report. This report was on the potential impact and what can be done about it. They’ll also be doing some research this summer. This report should be out by this fall for comments. So they are doing some of the work, and they are looking at some of the issues that the Members here are talking about specific to this project.