Thank you, Mr. Speaker. I’ll have to interpret that to mean completion of this road as we saw and budgeted for or I’m sure the number of issues he’s raised in his Member’s statement are what he’s suggesting that we incorporate. At this point, we have targeted $2 million for this upcoming year and a further $2
million to do work on the Dettah road. The work will include engineering work, the surveys and all the designs and gravel production. As the Member knows, this road had very little in terms of real engineering structure and was constructed many years ago when most of the material was clay, and at that time there was very little in terms of consideration for drainage. So that’s the work that we’re focusing on. Down the road we may look at going the final step and look at putting a dust suppressant and possibly chipseal or something of that nature. Thank you.