We do have a final approved design on the bridge. We have been working since last August to get that. It has been very detailed, very involved. It has gone through two separate independent reviews and we are now very comfortable with the design that we have going forward and it is complete and finalized.
There are three aspects of that design that still remain to be finalized and there is a plan for doing that over the next couple of months. Those are relatively minor items representing about 2 percent of the value, that is why there is a line item there titled Miscellaneous Construction for $2.2 million that would be used to address the three minor items that are not yet finalized. Those three items are for lighting electrical, to finalize that and we are still waiting a little bit because we want to do some work on the toll collection system and see how that relates, and the design of a catwalk underneath the bridge to facilitate operations and maintenance inspections and then the final paving on top of the bridge, the design for that. Thank you.