This is page numbers 4889 - 4926 of the Hansard for the 16th Assembly, 5th Session. The original version can be accessed on the Legislative Assembly's website or by contacting the Legislative Assembly Library. The word of the day was million.

Topics

The Chair

The Chair Glen Abernethy

Highways, not previously authorized, $30.078 million.

Some Hon. Members

Agreed.

The Chair

The Chair Glen Abernethy

Moving along to page 17 still on the Department of Transportation, Transportation, continued, capital investment expenditures, marine, not previously authorized, $172,000.

Some Hon. Members

Agreed.

The Chair

The Chair Glen Abernethy

Road licensing and safety, not previously authorized, $921,000.

Some Hon. Members

Agreed.

The Chair

The Chair Glen Abernethy

Total department, not previously authorized, $39.729 million.

Some Hon. Members

Agreed.

The Chair

The Chair Glen Abernethy

Let’s move along to page 18, Industry, Tourism and Investment, capital investment expenditures, tourism and parks, not previously authorized, $1.372 million.

Some Hon. Members

Agreed.

The Chair

The Chair Glen Abernethy

Total department, not previously authorized, $1.372 million.

Some Hon. Members

Agreed.

The Chair

The Chair Glen Abernethy

Moving along to page 19, Environment and Natural Resources, capital investment expenditures, corporate management, not previously authorized, $211,000.

Some Hon. Members

Agreed.

The Chair

The Chair Glen Abernethy

Forest management, not previously authorized, $184,000.

Some Hon. Members

Agreed.

The Chair

The Chair Glen Abernethy

Total department, not previously authorized, $395,000.

Some Hon. Members

Agreed.

The Chair

The Chair Glen Abernethy

Okay. Does committee agree that we have concluded consideration of Tabled Document 43-16(5), Supplementary Estimates No. 3, 2010-2011 (Infrastructure Expenditures)?

Some Hon. Members

Agreed.

The Chair

The Chair Glen Abernethy

Mr. Ramsay.

David Ramsay

David Ramsay Kam Lake

Thank you, Mr. Chair. I move that consideration of Tabled Document 43-16(5), Supplementary Estimates No. 3, 2010-2011 (Infrastructure Expenditures), be now concluded and that Tabled Document 43-16(5) be reported and recommended as ready for further consideration in formal session through the form of an appropriation bill. Thank you, Mr. Chair.

The Chair

The Chair Glen Abernethy

Thank you, Mr. Ramsay. A motion is on the floor and is being distributed.

Some Hon. Members

Question.

The Chair

The Chair Glen Abernethy

Question is being called.

---Carried

Sergeant-at-Arms, please escort the witnesses out of the Chamber and thank you very much to the witnesses for joining us today.

Based on the previous decision of committee, next on our agenda is Tabled Document 4-16(5), Executive Summary of the Report of the Joint Review Panel for the Mackenzie Gas Project, and we will open the floor to general comments. Mr. Bromley.