Mr. Speaker, I also wanted to ask a question today about concerns over the design. Also in the Auditor General’s report it talks about concerns over the design being brought forward by the Department of Transportation and somebody somewhere overriding a recommendation of the department to continue to waive the requirement for the design being done and to proceed with construction. It is paragraph 27, if the Minister wants to have a look at that. I would like to ask how that could happen. Thank you.
David Ramsay on Question 567-16(5): Auditor General’s Report On The Special Audit Of The Deh Cho Bridge Project
In the Legislative Assembly on March 3rd, 2011. See this statement in context.
Question 567-16(5): Auditor General’s Report On The Special Audit Of The Deh Cho Bridge Project
Oral Questions
March 2nd, 2011
See context to find out what was said next.