Thank you, Mr. Chair. My other question is in regard to the YK Airport, the wood pellet boiler, $660,000. Just going ahead in regard to the following page, I noticed there’s one point something million for the same facility. So I’d just like to know, it’s on page 13, the combined services building, $1.026 million. I’m just wondering, is that the same capital expenditure and how close are we, again, to completing the construction of that combined services building at the airport?
David Krutko on Committee Motion 1-16(6): Concurrence Of Td 7-16(6), Supplementary Estimates (Infrastructure Expenditures), No. 6, 2010-2011, Carried
In the Legislative Assembly on May 11th, 2011. See this statement in context.
Committee Motion 1-16(6): Concurrence Of Td 7-16(6), Supplementary Estimates (Infrastructure Expenditures), No. 6, 2010-2011, Carried
Consideration in Committee of the Whole of Bills and Other Matters
May 10th, 2011
See context to find out what was said next.