I guess I would call on all of the House to ensure that the Auditor General’s guidance is reflected in that policy before it’s approved.
Just my last question here. Given that $17.4 million has been spent and the development costs for the project were estimated to be $20 million, we’re now over 80 percent expended on the budget for developing the project. Although it’s on hold, I understand from the chairman of the Power Corporation that development, or perhaps the Hydro Corporation development, is still proceeding or explorations towards a restructuring and so on. Again, presumably that would engender new costs for essentially a new project. Can we expect that the Minister will be coming forward with another supp on these, and at what point on these projects do we say stop and desist and let’s give up if we’re beating a dead horse, sort of thing?
Again, I’m just sensitive to our financial situation pressing up against our debt limit and so on. Comments from the Minister would be appreciated. Thank you.