When this project was first proposed there was an estimate given to the PUB as this project had to be filed through them as well. The targeted impact was in the neighbourhood of up to between 1.5 to 2 cents per kilowatt hour. So that was budgeted prior to any changes in the budget. With this change we’re looking at 2.5 cents per kilowatt hour impact in this region. That does affect the rest of the communities because our Power Support Program, as we’ve changed it, is based on the Yellowknife rate. Thank you.
Floyd Roland on Question 108-16(6): Increased Costs To Replace Bluefish Dam
In the Legislative Assembly on May 18th, 2011. See this statement in context.
Question 108-16(6): Increased Costs To Replace Bluefish Dam
Oral Questions