Mr. Speaker, it’s not going to cost us any more money. That is the message that we have to get out there. If the bridge wasn’t going to open this fall, we would be faced with a minimum of $9 million for various costs associated with the delay. We would also have hanging over our heads a number of claims, a myriad of claims that exist for the last couple of years with Ruskin.
What we have done is get some budget certainty and, again, that budget certainty, we have $13.7 million left in the construction budget. We are looking for another between $7.2 million and $9.5 million to add to that $13.7 million to complete the bridge by this coming November. That’s something that we are intent on doing. We need to find a way forward. We need to get this project completed. That is our full intention to do just that. Thank you.