Thanks, Madam Chair. There were some delays. There were some issues around design and whatnot and some budget issues as well. I believe for certain aspects of it, in particular the chimney systems, a contract has been awarded. The kitchen is out for tender right now, but with the chimney we were notified, I believe it was last week, about some issues that they’re having with the chimneys that I shared with Members. Those issues have been dealt with and they should be proceeding with the chimney and moving to the kitchen once the RFP is concluded. Just as a note, the work is scheduled to be completed this fiscal year.