Thank you, Mr. Chair. A portion of the $65 million will be used for the geotechnical and then for a Source 177 upgrade. That would total about $25 million, and that work, we are planning to negotiate. There’s the rest of the money, the $40 million, which will first be used to take us from 85 percent to 100 percent design, to get us through the regulatory process, and then to begin construction on the new sections of the road, the 120 kilometres that remain, to begin that construction this coming winter.
Russ Neudorf on Committee Motion 19-17(4): Concurrence Of Supplementary Estimates (Infrastructure Expenditures), No. 3, 2012-2013, Carried
In the Legislative Assembly on March 11th, 2013. See this statement in context.
Committee Motion 19-17(4): Concurrence Of Supplementary Estimates (Infrastructure Expenditures), No. 3, 2012-2013, Carried