When the Giant Mine Remediation Project was initiated, the GNWT’s share that we put on for a lot of the surface work, $23 million back in 2004-05, and as the remediation project proceeded, the issue of the road became relevant and to the fore. So what was a decision that was made, that $23 million was in O and M. So it was agreed that we would reprofile and reclassify $17 million of that $23 million to cover the cost of this road that’s being put in around Giant Mine. So it’s not detracting from other capital projects, it’s not being taken from a pot that was dedicated for other areas or other communities or other specific projects, it’s tied directly to the broader Giant Mine Remediation Project.
Michael Miltenberger on Consideration in Committee of the Whole of Bills and Other Matters
In the Legislative Assembly on May 30th, 2013. See this statement in context.